Process mapping basics: five symbols, swimlanes, and the two clocks

The five flowchart symbols people actually use, swimlanes that show where the handoffs are, and the two clocks (work time, wait time) that tell you which step to fix first: one page.

Get the free PDF

One page, print-ready, free to share. No signup needed.

Download the PDF

An approval took eleven days. The people involved worked on it for about one day in total. The other ten days it sat in someone's inbox. This page covers the five symbols a process map actually needs, swimlanes that show where the handoffs are, and the two clocks that tell you which step to fix first. The print-ready A4 PDF is at the bottom.

Five symbols

  • Oval: start and end.
  • Box: a step someone does.
  • Diamond: a decision, yes or no.
  • Document: a form, a mail, a ticket.
  • Arrow: the handoff. Waiting lives here.

BPMN has dozens more. You will not need them for a map whose job is to show a team where the time goes.

Swimlanes

  • One lane per role. Every arrow that crosses a lane is a wait.

Draw the lanes first (requester, manager, finance, director), then place each step in the lane of whoever does it. The map now shows the handoffs without a single word of explanation.

Two clocks

  • Work time: hands on the step. About one day in total.
  • Wait time: ten of the eleven days. Fix this first.

The approval, two clocks

Map the steps, then write both clocks next to every arrow. The map is done when the waits are on it.

StepLaneWorkWait before it
request filedrequester2 h0
manager reviewmanager1 h3 days
budget checkfinance4 h5 days
sign-offdirector1 h2 days
total4 lanes1 day10 days

Eleven days end to end. Making the budget check twice as fast saves two hours. Clearing the queue in front of it saves five days.

Where the numbers come from: the timestamps on the ticket or the mail thread give the wait; a few people telling you how long the step takes when they get to it gives the work. Three or four real examples are enough for a first map.

The trap: the map that fixes the wrong thing

Three ways a process map looks finished and changes nothing.

  • Mapping the work only. People speed up the 4-hour budget check. The 5-day queue in front of it stays.
  • The happy path only. The diamond has a "no" branch. Rejections loop back to the requester: ask how often, and add that wait.
  • Drawn from the desk. The official process and the real one differ. Walk it with one person from each lane.

The fix for a wait is rarely a faster person. It is a smaller batch (finance checks budgets daily instead of in a Friday pile), a clearer handoff (the request arrives complete, so it is not sent back), or one lane fewer (the director delegates sign-off under a threshold).

What to bring to the meeting

One page: the swimlane map with both clocks on it, the total of each clock, and one sentence per wait saying why the queue forms. That is the whole document. The business case (sheet 076) comes after, once the team has agreed which wait to attack.

The full page is a free print-ready A4 PDF: five symbols, swimlanes, two clocks.

Frequently asked questions

What are the basic symbols of a process map?
Five cover almost every map: an oval for start and end, a box for a step someone does, a diamond for a decision with a yes and a no branch, a document shape for a form, mail or ticket, and an arrow for the flow between steps. The arrow is where waiting lives.
What is a swimlane in a process map?
A horizontal band for one role or team. Each step sits in the lane of whoever does it. Every arrow that crosses from one lane to another is a handoff, and handoffs are where work waits.
What is the difference between work time and wait time?
Work time is the time someone has their hands on the step. Wait time is the time the item sits in a queue before the step starts. In most office processes, wait time is 80 to 95% of the total, which is why speeding up the work rarely helps.
How do you find the bottleneck in a process?
Write both clocks next to every step and look for the longest wait, not the longest work. The step with the biggest queue in front of it is where the time goes. Then ask why the queue forms: batch size, unclear handoff, one person approving everything.